Critical path method: find the tasks that set your end date

The critical path is the longest chain of linked tasks. It sets the earliest finish. A delay on it delays the whole project.

Guide 03 of 21 · Part of the integrated planning series · 5 minute read
MandateOutcomesPeopleWorkTimeMoneyUncertaintyAdoption

These are the eight planning threads the Krong course is built around. The highlighted ones are covered here. What are the planning threads?

In one lineFloat is the time a task can slip without moving the end date. Critical tasks have none.

Three ideas to know

  1. Predecessors. A task cannot start until the tasks it depends on finish.
  2. Forward pass. Work left to right to find the earliest start and finish of every task.
  3. Backward pass. Work right to left from the end date to find the latest start and finish. Float is the gap between the two.

The Caldera Freight schedule

Caldera Freight has 35 work packages and a 60-week duration. Eighteen of them have zero float. They form the critical path.

1.1.11.1.31.1.41.3.21.5.31.6.3 Week 0Week 60
Orange bars are critical: no slack. The grey bar, governance setup (1.1.4), has 32 weeks of float, shown as a dashed outline.

Look at the two rows in the middle of the chart. Model development and testing (1.3.2) is critical. Governance setup (1.1.4) is not. The PMO could start it late and the project would still finish on time, up to a point.

What to do with it

Why it is an integrated planning tool

A critical path is only as good as the data under it. Durations come from estimates. Predecessors come from the work breakdown. Owners come from the RACI matrix. Risks matter most when they sit on a critical task. In Caldera Freight, R-03 (algorithms may not reach the expected efficiency) attaches to component 1.3, where every work package is critical. It deserves tighter control than a risk on work with 24 weeks of float.

How Sen helps

Sen recalculates the path every time you change a duration or a link. The Gantt chart marks critical tasks in tangerine and shows float for the rest. You can zoom from one day to one month, and export the schedule to a task file for MS Project, Asana, monday.com or Jira.

Questions people ask

What is the critical path?

It is the longest sequence of dependent tasks in a project. It decides the earliest possible finish date.

What is float or slack?

Float is how long a task can be delayed without delaying the project end date. Tasks on the critical path have zero float.

Can a project have more than one critical path?

Yes. If two chains have the same total length, both are critical. Sen marks every task with zero float.

See it in a real plan

Open Sen and explore the Caldera Freight example. Every figure on this page comes from it. Copy it, change a task, and watch the plan move together.

Open Sen, free   About the course

Keep reading

GUIDE 02
Work breakdown structure
Break a project into work packages once, then reuse the same IDs for schedule, budget, risk and ownership.
GUIDE 05
Risk scoring
Score probability and impact, set priority bands, and connect each risk to the work and the contingency.
GUIDE 06
Earned value
Planned value, earned value, actual cost, SPI and CPI explained, with the Week 28 numbers from Caldera Freight.