Dependencies, link types and lags

A dependency says what must happen before a task can happen. Real plans use four kinds, and a lag on any of them.

Guide 13 of 21 · Part of the integrated planning series · 5 minute read
MandateOutcomesPeopleWorkTimeMoneyUncertaintyAdoption

These are the eight planning threads the Krong course is built around. The highlighted ones are covered here. What are the planning threads?

In one lineFour link types and a lag are enough to describe how real work overlaps.
LinkMeaningExample
Finish to start (FS)B starts after A finishesTest starts after build finishes
Start to start (SS)B starts after A startsTraining material starts once design starts
Finish to finish (FF)B finishes after A finishesTesting ends after the last build ends
Start to finish (SF)B finishes after A startsOld system runs until the new one starts

Finish to start is the default and the most common. The others let you overlap work honestly, instead of faking it with shorter durations.

Lag and lead

A lag is a wait on a link. Concrete must cure for two days before the next task: that is a finish-to-start link with a two day lag. A negative lag, called a lead, lets a task start before its predecessor ends.

A lag does not have to be shorter than the task. It is a wait between two tasks, not part of either task's own duration, so a two day task can follow a ten day wait. If the lagged task is on the critical path, the project end moves by the same amount and the task stays critical. Tasks off the path gain float, but their durations do not change.

How to type it in Sen

In the Predecessors column, type the task ID, then an optional link type and lag.

You typeIt means
1.2.1Finish to start, no lag
1.2.1SS+2Start two units after 1.2.1 starts
1.3FF-1Finish one unit before 1.3 finishes
1.4FS+3Start three units after 1.4 finishes

The unit is whatever your plan uses: days or weeks. Sen recalculates the critical path and float straight away.

Why it matters for integrated planning

A dependency is a link between two parts of the work. If the links are wrong, the dates are wrong, and so are the cost profile and the resource loading built from them. Getting them right is the cheapest way to improve the whole plan.

Questions people ask

Which link should I use by default?

Finish to start. Use the others when work genuinely overlaps.

Can a lag be negative?

Yes. A negative lag is a lead. Use it sparingly, because it hides risk.

Does Sen allow loops?

No. A loop has no valid schedule, so Sen shows an error until you break it.

See it in a real plan

Open Sen and explore the Caldera Freight example. Every figure on this page comes from it. Copy it, change a task, and watch the plan move together.

Open Sen, free   About the course

Keep reading

GUIDE 03
Critical path
Which tasks have no slack, how float works, and how to read a critical path on a real schedule.
GUIDE 14
Milestones and gates
A milestone marks a date that matters. A gate marks a decision. Both take no time, and both belong on the schedule.
GUIDE 15
Resource loading
A schedule can be correct and still impossible. Resource loading shows when one team is asked to do too much in the same week.